The stages of building a house begin once the design is approved and the contract is signed, although builders group and name the steps on site differently.
The stages of designing a house come before the build and have their own answer. This guide follows the build itself, from approval to handover, the work we carry out as custom home builders in Sydney.
What are the stages of building a house?
The NSW Government's MyHome planner names six build phases: site preparation, laying the foundations, constructing the frame, lock-up, fit-out and practical completion. This guide joins site preparation to the foundations to make five steps, each ending at something you can see on site:
- Site preparation and foundations: the site is fenced and the foundations are poured.
- Frame: the frame and external walls are standing.
- Lock-up and services: the doors, windows and roofing are in and the house can be locked.
- Fit-out and finishes: the lights, tapware, cabinets and benchtops are installed.
- Practical completion, the occupation certificate and handover: three separate milestones that finish the build.
Why do some builders list six or seven stages?
Some builders count site works and the slab as separate stages, which is how a six-stage list and a seven-stage list can describe much the same build.
What matters is the list in your own contract. The NSW Government's guidance on building contracts says the stages of work in a progress payment schedule must be described in clear and plain language. Read those stage names against the drawings before you sign, so you know what each payment is for and what should be finished on site when it falls due.
What has to happen before building starts?
Before anyone breaks ground the home needs its approval, a signed contract and, in most cases, its insurance.
On the DA (development application) route you need a construction certificate, which NSW Planning describes as building approval from your council or a private certifier. A CDC (complying development certificate) instead combines planning and construction approval when the home meets the relevant standards, so choosing between a DA and a CDC decides which paperwork you face. Either way the owner engages the principal certifier, not the builder.
icare asks homeowners to check that the builder holds home warranty insurance for their project before paying a deposit or allowing work to start. That cover is needed for most residential work over $20,000 unless an exemption applies.

Site preparation and foundations
The site is prepared first, which can mean levelling the ground, removing trees or taking down an existing house. Temporary fencing then goes up around it for safety. The foundations are then measured out and poured, with under-slab drainage, moisture barriers and termite protection prepared at the same stage.
The principal certifier inspects at this point, since Building Commission NSW explains that the certifier carries out mandatory inspections during construction. The certifier isn't a project manager or site supervisor, which is why some owners also bring in an independent building inspector.
Frame, lock-up and services
The frame and external walls go up next while licensed electricians and plumbers install the wiring and pipes for power, water and gas. The frame is one of the certifier's usual inspection stages. Lock-up is reached when all the doors, windows and roofing are installed and the home can be locked and kept secure. Plasterers, tilers, carpenters and the other trades can then work inside out of the weather.
Fit-out and finishes
Fit-out is where the house starts to look like the drawings, as the lights, power points, tapware, cabinets, benchtops, baths, basins and shower screens go in. Wet area waterproofing is another of the certifier's usual inspections.

Practical completion, the occupation certificate and handover
These are three separate milestones. Practical completion is a stage in your contract with the builder, whose own definition binds you both. The NSW planner places it where the painting, final detailing and fencing are done and the house is ready for its pre-handover inspection. The occupation certificate follows the certifier's final inspection and authorises you to occupy and use the new house. Handover is a guided walk through the house, its systems and its warranties.
How payments follow the stages
Where your contract pays by stage, each payment follows the completion of a stage it specifies and is set as an amount or a percentage of your own contract price. Ask how each stage in the payment schedule matches one of the checkpoints above, such as the foundations being poured or the house reaching lock-up.
Plan your custom home
Tell us about your site and where the design stands so we can show you how each stage would run for your home.
Questions
Which inspections does the certifier carry out?
The inspections are usually listed on your approvals. They generally cover the piers and footings, the slab, the frame, stormwater, wet area waterproofing and a final inspection before the occupation certificate.
Can I visit the site during construction?
Yes, with your builder's permission. The NSW Government suggests a supervised walkthrough at key stages, arranged with the site supervisor, because entering a working site unsupervised may breach your contract.
Can a builder ask for a progress payment early?
No. The NSW MyHome planner says a builder cannot ask for any progress payment in advance of the work being carried out. Payments made outside your contract's schedule may not be covered by home building compensation.